09.00 Arrival at the site.
09.10 The pit is dug. In the meantime a representative from an authorised body rechecks whether the coating of the tank has any defects.
09.20 First the anodes are embedded in the pit.
09.40 The tank is placed in the pit, and the pit carefully filled with loose, stone-free earth.
10.00 The detachable foot rests on which the tank was resting during transportation are placed upside down on top of the tank.
10.20 A heavy concrete block is placed on these foot rests. This is to prevent the tank being pushed upwards by the groundwater.
10.30 Pause.
10.40 Manifold fitted. This manifold has all the requisite fittings, such as a gauge, a pressure-relief valve, a filling valve and a gas offtake valve.
11.00 Pressure regulator, isolation valve and remote wireless content recorder fitted cover placed on the access pit.
11.20 Pit topped up with earth and finished off.
12.00 Depart, leaving behind one satisfied customer.